The building of cutting line of hot strip in coils is carried out in JSC “Kirov non-ferrous metals processing plant”.

April 1, 2015

In the frame of the investment program of modernization of rolled procuring capacities, JSC “Kirov non-ferrous metals processing plant” proceeded to the next stage - installation of cutting line of hot strip in coils of a width of 1050 mm.

At present time the experts of JSC “Kirov non-ferrous metals processing plant” in cooperation with contractors conduct building of cutting line manufactured by the company "MINO" (Italy). Up to date, the preliminary works were held on the platform: the not used in production equipment was dismantled, dirt works for line foundation was made. Works are carried out in terms of schedule and with appropriate quality.

With the completion of this stage of the investment program the plant will be able to produce copper and brass sheet and strip width of 1050 mm, corresponding to international quality standards.

This website uses cookies to gather statistics on the website traffic and usage. By continuing to browse our website you accept the use of cookies.